Micro-watershed in the Shivalik hills will be managed to provide the water supplies for various users.

Target: Development of micro-watersheds through construction of 18 water harvesting dams.

17 of 18 dams planned in the Overall Work Plan have been completed. 2 more are under construction and will be completed by the end of year 2006-07.

 

Cost per Ha. Rs. 49,705

Combined Storage

Combined Catchment Area

Combined Command Area

Combined Cost

254.89 Ha. meter 808 Ha. 807 Ha. Rs. 40,112,569

 